Sabah deputy chief minister says highway progress is higher than audit figure
Dr Joachim Gunsalam stated the 11.4% completion rate in the Auditor-General’s Report only counts fully handed-over packages and does not reflect actual physical progress.

The 11.4% completion rate for the Sabah Pan Borneo Highway project highlighted in the recent Auditor-General’s Report does not reflect the actual physical progress on the ground, according to Sabah deputy chief minister Dr Joachim Gunsalam. The figure only measured the number of fully handed-over packages, which accounted for just four of the 35 packages under Phase 1 of the project.
Although the 11.4% figure is correct in terms of handed-over packages, it does not reflect overall progress as other packages are actively being built, with some alignments recording between 90%-93% physical progress, he told reporters on the sidelines of the Gabungan Rakyat Sabah (GRS) convention. Construction work has continued to show positive progress, with eight packages spanning 179km proposed to be opened to motorists in stages by the end of the year.
Regarding the Variation Order (VO) issue reported to have exceeded RM514 million, Dr Joachim Gunsalam clarified that approval for the additional cost falls under the jurisdiction of the federal works ministry and finance ministry, not the state government. The Sabah public works department only acts as the technical implementing agency and has no authority to approve the VO. The VO was necessitated by technical factors such as Sabah’s unpredictable hilly topography involving slope stability issues, and swampy and peat soil structures that change every one to 1.5km.
Project delays were affected by the termination of the previous Project Delivery Partner (PDP) model, which forced a shift to the conventional method, making the project reliant on annual federal allocation approvals. In addition to the impact of the Covid-19 pandemic in 2021, most contractor appointments for new packages could only be finalised between February 2024 and January 2026 after the federal government reconsidered the implementation method.
Delays also stemmed from a time-consuming land acquisition process. The government did not take a draconian approach but instead allowed landowners to appeal for compensation, while also acknowledging challenges related to the performance of some contractors.
Key facts
- The 11.4% completion rate only accounts for four of the 35 packages under Phase 1 of the Sabah Pan Borneo Highway.
- Some highway alignments have recorded between 90%-93% physical progress.
- Variation Order costs are reported to have exceeded RM514 million.
Three perspectives
Neutral
The 11.4% completion rate for the Sabah Pan Borneo Highway project reflects only the number of fully handed-over packages.
Positive
The state government views the audit findings positively and has taken steps to address them with support from the federal government.
Negative
Project delays were caused by the termination of the Project Delivery Partner model, the Covid-19 pandemic, and time-consuming land acquisition processes.