Ten communities in Micoud North may see improved water supply by December as the Patience Water Supply Redevelopment Project nears completion. The project aims to increase water production and reduce turbidity.
The Patience Water Supply Redevelopment Project is approximately 85 per cent complete, according to Maurice Norville, Head of the Project Management Unit at the Water and Sewerage Company. Norville said the project is expected to be completed by December 2026.
The project includes the reconstruction of the Patience Water Treatment Plant, which supplies water to ten communities, including St Marie, Patience, and La Haut. The upgrades aim to increase water production and improve the water supply to these communities.
The new intake structure on the Fond River is already complete, and the new raw water pumping station is about 90 per cent complete. Pipeline replacements are approximately 75 per cent complete, and the new treatment plant arrived in Saint Lucia in August.
The project is funded by the CARICOM Development Fund and costs US$2 million. The update comes as WASCO and the Met Office have reported reduced rainfall and growing concerns about water availability in communities across Saint Lucia.
Met Office Director Vigil Saltibus said this year's rainy season has been drier than ideal, with rainfall deficits being observed across the island. The south, including Micoud, has recorded some of the lowest levels.
Acting Chief of Operations Tera Victor said WASCO is currently using water trucks and adjusting valves within the distribution network to direct available water to communities in need.
The project's completion is expected to bring relief to the ten communities in Micoud North that have been struggling with low water levels and turbidity during the dry season.
Key facts
- The Patience Water Supply Redevelopment Project is approximately 85 per cent complete.
- The project is expected to be completed by December 2026.
- The project includes the reconstruction of the Patience Water Treatment Plant.
- The project is funded by the CARICOM Development Fund and costs US$2 million.
Three perspectives
Neutral
The project's completion is expected to improve the water supply to ten communities in Micoud North. However, the reduced rainfall and growing concerns about water availability in communities across Saint Lucia may still pose challenges. The situation will be monitored closely.
Positive
The project's completion will bring significant relief to the communities in Micoud North that have been struggling with low water levels and turbidity. The increased water production and improved water supply will have a positive impact on the daily lives of residents.
Negative
The delayed completion of the project may have caused inconvenience to the communities in Micoud North. The reduced rainfall and growing concerns about water availability in communities across Saint Lucia may still pose challenges even after the project's completion.
Your week in news, every Wednesday
The biggest stories of the week for your edition, in your inbox every Wednesday morning, your time. Free, and you can unsubscribe at any time.