Birmingham New Street and London Paddington to close for festive engineering works

Major rail projects worth £152m will cause station closures and service disruptions across the UK during the Christmas period.

Birmingham New Street and London Paddington to close for festive engineering works
Photo: The Guardian

Birmingham New Street station will close for five days from the start of Christmas Eve until 29 December 2026 to replace overhead power supplies. No trains will stop or pass through the station during this time, and rail replacement buses will serve the city centre.

London Paddington station will also be affected by work on lines leading into the station, including replacing a junction near Slough. Most Great Western services to Wales and the west of England will start and finish at Reading from 27 December until 4 January, with some services diverting around Oxford to London Euston.

Engineering works on the Great Eastern mainline out of London Liverpool Street will result in a 10-day closure from Christmas Day for track replacement in east London. This means no Greater Anglia or Elizabeth line trains will run through the area, and there will be no direct trains from Norwich to London.

Other disruptions include part closures on the east coast mainline on Christmas Eve, where work at Doncaster will mean trains between London, north-east England and Scotland are partly replaced by buses from Newark to York, adding two hours to journeys. TransPennine services between Leeds and Manchester will also be slowed for six weeks from Christmas Day due to the closure of Huddersfield station.

Network Rail said the Christmas period is the best time to conduct the £152m of essential works to improve reliability and capacity because services generally stop on 25 and 26 December.

Anit Chandarana, Network Rail’s group director for system operator, said the team has worked with train operators to keep services running on the busiest travel days and urged passengers to check their journeys before setting off.

Key facts

  • Birmingham New Street will be closed from Christmas Eve until 29 December to replace overhead power supplies.
  • Major works at London Paddington and Birmingham include £152m of improvements to reliability and capacity.
  • The Great Eastern mainline out of London Liverpool Street will close for 10 days from Christmas Day.

Three perspectives

Neutral

Network Rail is carrying out £152m of engineering works during the festive period, including closures at Birmingham New Street and London Paddington.

Positive

Engineers hope to use the quieter festive days to complete major projects to improve rail reliability and capacity.

Negative

Passengers travelling between London, north-east England and Scotland may face two-hour delays due to bus replacements on Christmas Eve.

Your week in news, every Wednesday

The biggest stories of the week for your edition, in your inbox every Wednesday morning, your time. Free, and you can unsubscribe at any time.

Choose your news coverage

Please choose and confirm your coverage.

All sections

Edition