NextDC expansion delayed by community opposition to power poles

The West Footscray data centre expansion has been pushed back to the 2027/2028 financial year after Jemena suspended power pole upgrades.

NextDC expansion delayed by community opposition to power poles
Photo: The Guardian

NextDC has told investors that plans to double the size of its West Footscray data centre have hit an obstacle after community members objected to 22-metre-high power poles. The company told the Australian Stock Exchange on Wednesday that delays to electricity provider Jemena’s upgrade of the power poles would push the expansion back to the 2027/2028 financial year.

Jemena has suspended the works due to safety concerns, lack of access to sites arising from community and stakeholder opposition, and because the local council did not approve the building of the 22-metre-high poles. These poles would be an increase from the 11 metres currently in place. NextDC and Jemena are considering other options, including underground power connections or alternate pole locations through industrial zones.

The expansion is intended to increase the M3 site capacity from 60 megawatts to 225 megawatts, a level of processing power NextDC has already sold to customers. The total planned expansion is expected to double the size of the M3 site to 10 hectares once complete. Due to the deferred billing and delivery of contracted capacity in M3, NextDC reduced its net revenue guidance to between $475m and $500m from between $615m and $640m.

NextDC chief executive Craig Scroggie told investors on Wednesday that he expects the earliest approval for the expansion would be February 2027. He said the Victorian government is about to enter caretaker mode for the 28 November state election. Scroggie noted the application has been with the state government since February 2026 and attributed delays to the change of premier from Jacinta Allen to Ben Carroll and the associated cabinet reshuffle.

Residents in West Footscray have expressed concerns regarding the scale of the expansion, construction noise, and the potential use of diesel generators during power outages. Sean Brown, a West Footscray resident and Citizens of Tottenham member, said the community's goal was to ensure a fair outcome and a proper safety framework.

Key facts

  • NextDC's expansion of the M3 data centre in West Footscray is delayed to the 2027/2028 financial year.
  • Jemena suspended power pole upgrades due to community opposition and lack of council approval.
  • NextDC reduced its net revenue guidance to between $475m and $500m.

Three perspectives

Neutral

NextDC is exploring alternative electricity supply options, such as underground connections, following delays to the West Footscray site expansion.

Positive

NextDC said construction of the new data halls will continue despite the delay in grid supply from Jemena.

Negative

The expansion faces delays due to community opposition to 22-metre-high power poles and slower than expected Victorian government planning decisions.

Your week in news, every Wednesday

The biggest stories of the week for your edition, in your inbox every Wednesday morning, your time. Free, and you can unsubscribe at any time.

Choose your news coverage

Please choose and confirm your coverage.

Next storyData centre expansion could add 39 million tonnes of emissions, Climate Council warns

All sections

Edition