High court orders LHDA to pay M89.9-million to LHWP communities
The Lesotho Highlands Development Authority must pay 20 community associations within 90 days following a 13-year delay in compensation for Phase 1 losses.

The high court ordered the Lesotho Highlands Development Authority (LHDA) to pay M89.9-million within 90 days to communities affected by the Lesotho Highlands Water Project (LHWP). The payments will go to 20 community associations, mostly from Thaba-Tseka, with amounts ranging between M16.2-million and M848,000.
The total amount has increased by 8% since 2013, when the LHDA stopped payment of a second tranche of compensation. Communities lost grazing land, riverine ecosystems and their sources of firewood, fish, wild vegetables and medicinal plants.
The LHDA had previously paid a first tranche in 2003 and 2004. The LHDA had stopped payments in 2013, citing a consultant's monitoring report that claimed there was no evidence of compensable losses.
The associations wrote to the LHDA in November and December 2025 to initiate negotiations after learning of the judgment. The LHDA then opened negotiations to settle the matter out of court and agreed on the M89.9-million payment.
In a separate matter, the Constitutional Court in May 2026 agreed with the LHDA that the court could decline litigation where adequate alternative remedies exist. The court found that the LHDA Act, the Land Act and LHWP compensation regulations provided mechanisms for compensation. The applicants in that case had more means of redress in the high court and the magistrates' court for alleged human rights violations.
Key facts
- The high court ordered the LHDA to pay M89.9-million to 20 community associations within 90 days.
- The total settlement amount has increased by 8% since the LHDA stopped second tranche payments in 2013.
Three perspectives
Neutral
The high court ordered the LHDA to pay M89.9-million to 20 community associations within 90 days.
Positive
The settlement provides compensation to 20 community associations, mostly from Thaba-Tseka, for losses such as grazing land and riverine ecosystems.
Negative
Communities faced 13 years of delays in receiving compensation for losses caused by the LHWP.