Electricity supply constraints could delay Johor data centre projects

Johor faces the most severe electricity supply constraints among major Asia-Pacific data centre hubs, according to US research firm BMI.

Johor’s data centre boom may be derailed by a looming electricity supply crunch, which could delay the rollout of projects in the southern state, according to US research firm BMI. BMI, a Fitch Solutions company, said Johor is expected to face the most severe electricity supply constraints among major Asia-Pacific data centre hubs.

The state's data centres would require about 30 terawatt-hours (TWh) of electricity annually by 2031, accounting for 18% of Peninsular Malaysia’s total electricity supply, up from 6% in 2026. Johor currently has about 825 megawatts (MW) of operational data centre capacity, with another 3.9 gigawatts (GW) expected to be added over the next three to five years due to demand for cloud computing and artificial intelligence (AI).

BMI warned that the rapid development of hyperscale data centres in Johor, Sydney, Melbourne and Batam could significantly increase electricity consumption over the next five years, potentially limiting power availability for other industries and households. The firm said Johor’s data centre industry could consume more than 90% of the additional electricity generated in Peninsular Malaysia in the next five years.

Access to electricity grid connections could become a greater obstacle than overall power generation availability, potentially delaying a significant number of planned projects. While Tenaga Nasional Bhd has planned a RM43 billion investment in grid upgrades, major electricity infrastructure projects typically require five to 10 years to complete. This creates a mismatch because data centre developments can progress considerably faster.

BMI expects Malaysia to increase its gas-fired electricity generation to meet growing demand, with some scheduled power plant closures potentially postponed to ensure sufficient supply. Developments with secured grid connections, committed tenants and strong financial backing are expected to be better positioned to meet construction and commissioning timelines.

Key facts

  • Johor's data centres are expected to require about 30 TWh of electricity annually by 2031.
  • Johor faces the most severe electricity supply constraints among major Asia-Pacific data centre hubs.
  • Data centre capacity in Johor is expected to grow by 3.9 GW over the next three to five years.

Three perspectives

Neutral

Johor's data centre industry is expected to account for 18% of Peninsular Malaysia's total electricity supply by 2031.

Positive

Tenaga Nasional Bhd has planned a RM43 billion investment in grid upgrades.

Negative

Electricity supply constraints and grid connection obstacles could delay the rollout of Johor's data centre projects.

Your week in news, every Wednesday

The biggest stories of the week for your edition, in your inbox every Wednesday morning, your time. Free, and you can unsubscribe at any time.

Choose your news coverage

Please choose and confirm your coverage.

All sections

Edition