Ireland requires data centres to fund renewable energy projects
New rules require tech firms to meet 80% of their energy demands through new renewable projects within six years.
Ireland has imposed a checklist for tech firms wanting to connect new data centres to the electricity grid. The policy requires companies to fund new renewable energy projects in Ireland to meet at least 80% of their energy demands. Companies must immediately provide their own power and have six years to get new renewable projects running to reach that 80% threshold.
Data centres accounted for almost a quarter of all electricity use in Ireland last year, a surge from 5% a decade ago. This usage is close to the amount of electricity used by all of the country’s households combined. Ireland leads the EU in data centre capacity with 31 megawatts per 100,000 people, which is more than triple the capacity of the Netherlands.
Ronan Kelly, chief executive of data center lobby Digital Infrastructure Ireland, said the country is leading the charge to take a responsible approach to building new infrastructure. Kelly described Ireland as the "canary in the coal mine" for the data centre dilemma in Europe.
Microsoft, a major investor in Irish data centres, said the clarity around renewables is a critical green light for continued investment. James O’Connor, site lead for Microsoft Ireland, said the company is moving to the design stage for a significant new development at Jiggenstown outside Naas. O’Connor said the company understands public concerns regarding electricity demand but sees an opportunity to tap into renewable energy through consistent demand.
Environmental NGO Friends of the Earth Ireland is part of a group lodging a case against the utilities regulator over the new rules. Rosi Leonard from the organisation said that while the policy looks good on paper, it is dangerous in practice because companies have a six-year glide path to build out renewables. Leonard stated it does not seem to hold up against Ireland’s climate commitments.
Key facts
- Data centres used almost a quarter of Ireland's electricity last year.
- New rules require data centres to meet 80% of energy demands through new renewable projects within six years.
- Ireland's data centre capacity is 31 megawatts per 100,000 people.
Three perspectives
Neutral
Ireland's new policy requires data centre developers to fund new renewable energy projects to meet 80% of their energy needs within six years.
Positive
Microsoft stated that clarity regarding renewables provides a critical green light to keep investing in Irish projects.
Negative
Friends of the Earth Ireland warned that the six-year glide path could allow new data centres to be powered mostly by fossil fuels like gas generators.