Da Nang to allow heavy trucks on Highway 14D until end of 2026
After testing transportation options, Da Nang will permit trucks with four axles or more to use the route connecting the Ho Chi Minh Highway with the Nam Giang International Border Gate.

Da Nang will allow trucks with four axles or more to travel on National Highway 14D until the end of 2026 after conducting a field survey and testing two transportation options. This decision follows a meeting on October 20 between leaders of Da Nang City and Sekong Province in Laos to discuss rerouting vehicles through the Dak Ta Ooc International Border Gate - Nam Giang during construction.
The renovation and upgrade project for National Highway 14D began in June 2026. The 65.37 km project starts at the intersection with Ho Chi Minh Highway in Ben Giang commune and ends at the Nam Giang International Border Gate area in La Deee commune. The total investment is 4,518 billion VND, using funds from the central government and city budgets.
Nguyen Van Thuong, Director of the Da Nang Investment and Construction Project Management Board for Transportation and Agriculture, said the investor is focused on accelerating project completion. He noted that the City People's Committee is directing the removal of obstacles, including completing documentation, determining land ownership, and developing compensation plans.
The project faces difficulties including heavy rain, wind, and the need to maintain traffic flow on a border road. Because heavy-duty vehicles continue to use the road while sections are under construction, there is a risk of structural damage. To address this, the construction unit is mobilizing manpower and machinery, with priority given to the section from Km0 to Km10+200 to complete two-layer asphalt concrete paving before the Lunar New Year.
Bui Duy Khanh, Project Executive Director of Xuan Quang Construction Joint Stock Company, said the contractor consortium has mobilized approximately 200 pieces of machinery along with engineers and workers. On November 9, workers were observed performing excavation, embankment, and leveling of the roadbed at the construction site in Ben Giang commune.
Key facts
- Da Nang will allow trucks with four axles or more on National Highway 14D until the end of 2026.
- The National Highway 14D renovation project has a total investment of 4,518 billion VND.
- The project length is 65.37 km, connecting the Ho Chi Minh Highway to the Nam Giang International Border Gate.
Three perspectives
Neutral
Da Nang is renovating National Highway 14D to connect the Ho Chi Minh Highway with the Nam Giang International Border Gate.
Positive
The investor is mobilizing manpower and machinery to accelerate progress, aiming to complete asphalt paving on priority sections before the Lunar New Year.
Negative
Heavy-duty vehicles using the road during construction increase the risk of structural damage and impact project quality and progress.