Traffic diverted in Ang Mo Kio as underground obstructions halt MRT tunnelling

The Land Transport Authority will implement traffic changes along Ang Mo Kio Avenue 3 from Nov 14, 2026, to May 2028 following the discovery of ground anchors.

Traffic arrangements along Ang Mo Kio Avenue 3 will be reconfigured from Nov 14, 2026, to May 2028 to facilitate recovery works. The Land Transport Authority (LTA) announced the changes after unexpected ground obstructions were found during tunnelling for the Cross Island Line (CRL). The eastbound carriageway between the AMK Hub pick-up and drop-off point and the Ang Mo Kio Avenue 8 junction will become a bus-only lane, while the westbound carriageway will be reduced from three lanes to two.

The obstructions, identified as ground anchors, were first detected in May when foreign materials were discharged from a tunnel boring machine (TBM). Between May and July, workers performed 100 cutterhead interventions to clear obstructions, extracting approximately 800kg of wire ropes and replacing 22 damaged cutters. These steel structures are installed in soil or rock to stabilize ground or support retaining walls.

LTA has suspended tunnelling works to investigate the full extent, origin, and impact of the obstructions on the construction timeline. Group director for the Cross Island Line Ng Choon Yeang said the priority is to understand the situation and address the obstructions safely before tunnelling resumes. Preliminary recovery works will include ground improvement to strengthen and stabilise the ground. The LTA and Building and Construction Authority (BCA) are working with project parties, including AMK Hub building contractors, to establish the circumstances of the anchors' presence.

Motorists heading towards the Central Expressway during the morning peak can use Ang Mo Kio Avenue 1 or Avenue 5, which may add one to five minutes to journeys. Those entering AMK Hub during peak periods should expect additional travel time of 10 to 15 minutes. Pedestrians will face diversions as the footpath on the eastbound side of Ang Mo Kio Avenue 3 will close, and ground-level access to the pedestrian overhead bridge will be unavailable. Pedestrians can instead use level two of AMK Hub to reach the bridge during mall operating hours.

The LTA stated that the wires were not detected during advance soil investigation works and were not reflected in engineering study drawings. The agency noted that soil investigation boreholes only sample ground at specific locations and intervals, making such anchors difficult to detect unless a borehole intersects them. LTA added there is currently no indication of similar undocumented anchors elsewhere along the CRL tunnel alignment.

Key facts

  • Traffic changes on Ang Mo Kio Avenue 3 will run from Nov 14, 2026, to May 2028.
  • Tunnelling works for the Cross Island Line have been suspended due to the discovery of ground anchors.
  • Between May and July, 100 cutterhead interventions were required to remove 800kg of wire ropes.
  • The eastbound carriageway near AMK Hub will be converted into a bus-only lane.

Three perspectives

Neutral

The Land Transport Authority is implementing traffic reconfigurations along Ang Mo Kio Avenue 3 to allow for investigations into underground obstructions.

Positive

LTA is deploying additional resources and conducting ground improvement works to ensure tunnelling can safely resume.

Negative

Motorists can expect peak-hour delays of up to 15 minutes near AMK Hub due to the road changes.

Your week in news, every Wednesday

The biggest stories of the week for your edition, in your inbox every Wednesday morning, your time. Free, and you can unsubscribe at any time.

Choose your news coverage

Please choose and confirm your coverage.

Singapore to transition to satellite-based road charging in 2027
Next storySingapore to transition to satellite-based road charging in 2027

All sections

Edition