Snowy 2.0 project cost rises to $25 billion as completion date slips to 2029
The Snowy 2.0 hydropower project could cost up to $25 billion, according to a major review by Snowy Hydro.

The Snowy 2.0 hydropower project could cost up to $25 billion, according to a major review by Snowy Hydro. The company has set a target cost of $22.2 billion but is allowing for an additional $3 billion if required. The project is now expected to be fully operational in late 2029, a delay from previous estimates.
Machine tunnelling is 65 per cent complete and major excavations are in their final stages. Work to build the new underground power station is underway with about 5,000 people working on the project. The project will link two dams through approximately 27 kilometres of tunnels and include an underground pumped hydro station.
Snowy Hydro chief executive Dennis Barnes said he was incredibly disappointed with the update. He noted the project is incredibly complex and described it as being off the charts even for mega projects. Barnes said the original contract had many flaws and the project was stalled, but he added that the project is now in its strongest position yet.
The project was first announced by the Turnbull government in 2017 with an initial price tag of $2 billion and an expected completion date of 2021. Costs have increased significantly over time, with a 2023 revision placing the estimate at $12 billion.
Delays and cost overruns have been attributed to the technical complexity of the project and challenges faced by the principal contractor, Future Generation Joint Venture. These include a specialist boring machine, Florence, becoming bogged in hard rock and global price rises for construction equipment, services, and staff.
Energy minister Chris Bowen and finance minister Katy Gallagher blamed the former Coalition government for poor design and cost projections. They stated the project remains necessary to strengthen Australia's national energy grid. Once complete, the expansion is expected to provide more than half of the total energy storage the grid needs by 2050.
Key facts
- The project cost could reach $25 billion, up from an original $2 billion estimate.
- Full commissioning and operation are now expected in late 2029.
- Machine tunnelling is currently 65 per cent complete.
Three perspectives
Neutral
The Snowy 2.0 project cost has been revised to a target of $22.2 billion with a potential maximum of $25 billion and a completion date in 2029.
Positive
Dennis Barnes said the project is in its strongest position yet and will provide half the storage capacity needed for renewables in Australia.
Negative
The project's cost has increased to approximately 12 times its original estimate and faces significant delays.