NextDC expansion delayed by community opposition to power poles
The company has pushed back its West Footscray data centre expansion to the 2027/28 financial year after Jemena suspended power pole upgrades.
NextDC told investors that plans to double the size of its West Melbourne data centre have hit an obstacle after community members objected to 22-metre-high power poles. The expansion of the M3 site in West Footscray is intended to increase capacity from 60 megawatts to 225 megawatts, which the company has already sold to customers.
Electricity provider Jemena has suspended works to upgrade power poles, which are essential for delivering the increased electricity required by the expanded site. Jemena suspended the works due to safety concerns, lack of access to sites arising from community and stakeholder opposition, and because the local council did not approve the building of the 22-metre-high poles, which are an increase from the current 11 metres.
NextDC reduced its net revenue guidance to between $475m and $500m from between $615m and $640m due to the deferred billing and delivery of contracted capacity in M3. The company and Jemena are looking at other options for supplying the increased electricity needs, including connecting via underground power connections or using alternate locations for poles through industrial zones.
NextDC chief executive Craig Scroggie told investors that the earliest approval for the expansion would be February 2027, as the Victorian government is about to enter caretaker mode for the 28 November state election. Scroggie said the application has been with the state government since February 2026 and blamed the change of premier from Jacinta Allen to Ben Carroll and the associated cabinet reshuffle for delaying approvals.
Local residents have expressed concerns regarding the scale of the expansion, construction noise, and the potential for diesel generators to be used during power outages. Sean Brown, a West Footscray resident and Citizens of Tottenham member, said the community's goal was to ensure a proper safety framework is in place and that they will continue raising concerns until they get a fair outcome for residents.
Key facts
- NextDC has pushed the West Footscray expansion back to the 2027/28 financial year.
- The company reduced its net revenue guidance to between $475m and $500m.
- The expansion aims to increase site capacity from 60MW to 225MW.
Three perspectives
Neutral
NextDC and Jemena are exploring alternative electricity supply options, such as underground connections, following the suspension of power pole upgrades.
Positive
NextDC said construction of the new data halls would continue despite the delay in grid supply from Jemena.
Negative
Community opposition to 22-metre-high power poles and delays in government planning approvals have stalled the expansion of the M3 site.